we are trying to determine what CTAs were created due to a CSM adding tasks in a Timeline activity.  Is there a way to denote which those are to build a report?
Photo of Heather Landgraf

Heather Landgraf

  • 1,068 Points 1k badge 2x thumb

Posted 9 months ago

  • 1
Photo of Hitesh Sharma

Hitesh Sharma, Employee

  • 4,096 Points 4k badge 2x thumb
Hi Heather,

There's a field called 'Source', which tracks from were the CTA was created.

For all the CTA's created from Timeline, we track Source as Activity, you can build a report as,
 

Let me know if anymore information is required.

Regards,
Hitesh
Photo of Heather Landgraf

Heather Landgraf

  • 1,068 Points 1k badge 2x thumb
thank you!