I have created a CTA for a QBR which is based on a Playbook containing multiple Tasks.  In this instance I wanted to add a couple of additional tasks to the CTA outside the normal Playbook scope.  I have done this but regardless of the order I sort the tasks in (date), the Tasks I have manually created appear at the bottom of the Task list.  I want them to sit in date order so that they arent missed.
Photo of Jon Harris

Jon Harris

  • 420 Points 250 badge 2x thumb

Posted 4 weeks ago

  • 2
Photo of Jagadeesh Kumar Paidimarri

Jagadeesh Kumar Paidimarri, Employee

  • 166 Points 100 badge 2x thumb
Hi Jon,

Could you please navigate to administration > tasks and apply display order as due date and see if this helps ?


Photo of Jon Harris

Jon Harris

  • 420 Points 250 badge 2x thumb
Thanks, it is set to 'Playbook Order' so that will be it.