Solved

Control which tasks get synced to SFDC

  • 9 June 2020
  • 4 replies
  • 108 views

Badge

Hey,

 

We recently enabled the GS to SFDC task sync, which works well, but we’d actually like to limit tye type of tasks that sync into SFDC, to only have renewal-related tasks synced. Is that something that can be done? Because I don’t see an option to apply a filter to the sync but perhaps I’m missing something.

 

Thanks!

icon

Best answer by aditya_marla 9 June 2020, 16:31

View original

4 replies

Hi @TalAmor ,

Thanks for sharing this. As of today, we cannot restrict the type of CTAs for which this option is available…if you are using a specific playbook for your renewal CTA’s you can turn on automatic sync only for this playbook (so that these tasks are automatically synced….but your users can still manually sync any tasks they want manually) 

Regards

Badge

That should work actually, how can I switch on automatic sync only for a particular playbook?

The last section of this article should have the necessary details:

https://support.gainsight.com/SFDC_Edition/Cockpit_and_Playbooks/Admin_Guides/10_Configure_and_Sync_Tasks_from_Gainsight_to_Salesforce#Sync_Playbooks_to_Salesforce

Let me know if you need anymore info

Badge

Worked like a charm, thank you! :)

Reply